Salik Data Center: 16 Cabinets
Power: 3x80KVA (N+1) Cooling: 4 CRAC units
Raised Access Floor Fire Detection & Suppression (FM 200)...
Access Control System CCTV System
Hydrogen Detection System
Earthing and Grounding SRG
Network Operating Center (NOC)
Electrical switchboards and Transformer
Lights and lighting control
16 Cabinets Hot Isle Containment
UPS System (N+1)
Cooling: 6x In Row units...
Raised Access Floor
Fire Detection & Suppression (Novec 1230)
Access Control System
CCTV System
Electrical switchboards and Transformer
Lights
10 Cabinets Hot Isle Containment ..
Power: 4x80KVA (N+1)
Cooling: 4 In Row and 2 CRAC
Raised Access Floor
Fire Detection & Suppression (Novec 1230)
Access Control
CCTV
Hydrogen Detection
Earthing and Grounding SRG
Network Operating Center (NOC)
Electrical switchboards and Transformer
Lights and lighting control
Environmental Monitoring
Power upgrade for Data Centers-Riyadh. Jeddah and Al Khobar:...
UPS System-6x 200 KVA and 2 x 160 KVA
Transformers
CRAC –Cooling units
Electrical switchboards
Floor Standing PDUs
Data Center:
24 Cabinets ...
Power: 3x120KVA (N+1)
Cooling: 4 CRAC units
Raised Access Floor
Fire Detection & Suppression (FM 200)
Access Control System
CCTV System
Earthing and Grounding SRG
Electrical switchboards and Transformer
Lights and lighting control
3 Cabinets U
PS System (N+1)
Cooling: 3x In Row units
Raised Access Floor
Fire Detection & Suppression (FM200)
Access Control System
CCTV System
Electrical switchboards and Lights
Installation of 20 Nos of 2500 KVA Transformers at District cooling plant...
Installation of Cable ladders
Installation of MV starters
Installation of control cabling
Two Data Centers: 10 cabinets and 4 cabinets:
UPS Systems
In Row Cooling: 6 CRAC units
Raised Access Floor
False Ceiling
Fire Detection & Suppression (FM 200)
Access Control System
CCTV System
Civil Works
Earthing and Grounding SRG
Electrical switchboards
Lights
Environmental Monitoring